ON NOW :


GAS NETWORK UPGRADE

Work to upgrade the gas network in the Burnfoot Road area of Hawick is to start next week.

The work involves replacing old metal gas mains and service pipes with new plastic pipes, ensuring a continued safe and reliable gas supply to the local community for many years to come.

Work has been planned in close consultation with the local authorities to reduce disruption as much as possible. The project will begin on Tuesday 4 May and will be carried out in phases, taking approximately 37 weeks to complete.

The first phase of the project will begin in Hillend Drive and over a 12 week period the road will be closed at its junctions with Charles Street, Galalaw Road and Fraser Avenue at separate times to allow engineers to work safely.

Throughout the project, it will be necessary to implement road closures and use temporary traffic lights to ensure everyone remains safe while work is carried out.

Phases:
Phase 1 – Charles Street, TD9 8BZ
3 May – 6 June (Road closure junction of Hillend Drive/Charles Street).
Phase 2 – Hillend Drive, TD9 8DT
19 May – 13 June (Road closure junction of Hillend Drive/Galalaw Road).
Phase 3 – Fraser Avenue, TD9 8DJ
7 June – 18 July (Road closure junction of Hillend Drive/Fraser Avenue).
Phase 4 – Kenilworth Avenue, TD9 8EQ
28 June – 25 July
Phase 5 – Burnfoot School, TD9 8ES
5 July – 22 August (2-way lights junction of Eildon Road/Kenilworth Avenue, road closure on Kenilworth Avenue outside the school.
Phase 6 – Kenilworth Avenue, TD9 8EQ
19 July – 8 August
Phase 7 – Eildon Road (112-82) TD9 8ET
26 July – 22 August
Phase 8 – Eildon Road (80-36) TD9 8ET
2 August- 22 August
Phase 9 – Burnfoot Road (37-63)
16 August – 17 October (2-way lights along Burnfoot Road).
Phase 10 – Burnfoot Road (101-63)
6 September – 17 October (Road closure Burns Road junction of Burnfoot Road, 2-way lights junction of Burnfoot Road/Fairhurst Drive.
Phase 11 – Fairhurst Drive (2-8) / Burnfoot Road (8-34)
28 September 17 October
Phase 12 – Fairhurst Drive (14-46)
18 October – 7 November 2021

Extra safety precautions are in place to protect SGN colleagues and communities from the virus. Colleagues will be keeping to social distancing guidelines on sites and SGN are asking communities to keep their distance too. There’s more information about the SGN coronavirus response on their website: sgn.co.uk/coronavirus

If any residents have specific enquiries about this project, please call 0800 912 1700 and the SGN customer experience team will be happy to help.